The purpose of this program is to plan the run priority and sequence of manufacturing order within a specific work centre. This panel displays operations for current work centre, sorted in sequence of run priority (descending), run sequence and planned start date.
Options
Header | Select this option to view the manufacturing order header. |
BOR | Select this option to view the manufacturing order bill of routing. |
Print op cards | Select this option to print the operation card. |
Reporting | Select this option to report time and quantity for the operation. |
Re-sch oper | Select this option to re-schedule the operation. The prompt for entering new planning start date or planning completion date will be displayed. |
Issue | Select this option to issue material to the operation. |
QC rep | Select this option to report a quality control result. This option is only valid if the MQC-OPER Manufacturing quality control at oper reporting function is activated in the Function control file, and if conformity criteria are connected to the operation. |
Function keys
Production reporting | Start the production reporting function. |
Minutes/Decimals | Toggle between hours and minutes and hours and decimals for the operation times. |
Reporting via TIME | Start the time/operation reporting function. This function key is only valid if IBS Time is installed and activated. |
Selection fields
- Work centre
- Tool 1
- Prod techn
- The production technology code.
- Tool 2
- Order number
- Oper
- Run pty
- Seq
- Plan start
- Str time
- The time when the operation is planned to be started. This field is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Plan compl
- Cmp time
- The time when the operation is planned to be completed. This field is only displayed if the MPL-TIME (Plan operation by date/time) function is activated in the Function control file.
- Description
- Remaining time
- The remaining time of the operation. This displays the run and labour time or machine time depending on the Workload planning type field for the work centre.
- Set-up
- The remaining internal set-up time.
- Remaining quantity
- The remaining quantity. Remaining quantity is manufacturing order quantity minus the reported approved quantity and the scrapped quantity for the current operation.
- St
- The code indicates the status of the operation.
- Tool 1
- Tool 2
- Prod techn
- The production technology code.
- Curr oper
- The last operation that has been reported for this order.
- Work centre
- The corresponding work centre for the last operation that has been reported.
- St
- The code indicates the status of the last operation that has been reported.